WHITEHORSE – Yukon Energy has terminated its contract with Texas-based SunGrid Solutions and will act as its own prime contractor to finish the $35-million Whitehorse grid-scale battery, the utility said Monday.
The Crown corporation said SunGrid failed to reach substantial completion within the time its contract required. Yukon Energy now expects the project to be finished in 2027, four years after the date it first gave when SunGrid was hired in 2022.
Paul Murchison, the utility’s vice-president of capital projects and engineering, said the contract called for the work to be substantially complete by this past July. Yukon Energy notified SunGrid it was in default and asked it to get the project back on schedule, Murchison told CBC News. “That didn’t happen,” he said.
Yukon Energy said it will now work directly with specialized subcontractors and buy the remaining equipment itself. Engineering firm Hatch, which has supported the project since 2020 and was involved in its original design, will provide project management and technical expertise. The work left includes fixing outstanding deficiencies, integrating equipment and systems, and completing testing and commissioning.
The utility said the goal remains to stay within the $35-million budget, but that is subject to confirming pricing for outstanding equipment and subcontractors. An independent review of the project is planned, and Yukon Energy said it expects to make the findings public when it is finished in 2027.
Ending the contract does not mean Yukon Energy is starting legal proceedings, the utility said, though it will keep pursuing damages and other remedies available under the contract.
Ottawa committed $16.5 million to the battery in 2019 through the Investing in Canada Infrastructure Plan. Yukon Energy said it has received $15 million so far, which leaves the remaining 10 per cent, or $1.65 million, withheld until the project is complete. That means the federal share covers about 47 per cent of the $35-million cost, so the territory’s ratepayers and utility carry the rest.
Murchison said the work SunGrid completed was done “reasonably well,” though not perfectly. He also said Yukon Energy was not planning to rely on the battery to shore up supply this winter even if the schedule had held, because the system will need to run through a winter before it can be depended on.
The battery is meant to replace four rented diesel generators the utility uses in winter, support more renewable power and help manage daily swings in electricity demand and supply. Once running, Yukon Energy said, it will help meet peak winter demand and make the territory’s grid more reliable.
Pressure on the Yukon grid has been a theme in our coverage. Yukon’s energy minister told MPs in Ottawa that ratepayers face another 53 per cent increase unless Ottawa shares the cost of grid upgrades, and the utility is paying households to cut winter peak demand through its Peak Smart Home program.
Questions can be sent to Yukon Energy at [email protected]. The utility’s news release and a CBC News report by Paul Tukker were the sources for this story.
If you find reporting like this useful, consider supporting Canada News Media, an independently owned Canadian newsroom.
Follow Canada News Media
Get the day's top Canadian stories and our two daily 60-second news videos wherever you scroll.
X Threads Facebook Instagram LinkedIn TikTok YouTube Pinterest Reddit Substack Flipboard Newsletter RSS