The federal government is seeking wider expropriation powers for the Alto high-speed rail line between Toronto and Quebec City, and Transport Minister Steven MacKinnon said Tuesday, Nov. 24, 2026, that the changes would not remove due process.
The draft measures are part of a notice of ways and means motion of more than 500 pages, put forward on Nov. 20 as the government prepares its budget implementation legislation. They are not law.
The proposal would let Ottawa transfer ownership of expropriated land directly to a private consortium and would send unresolved crossing disputes, such as those over split farms and municipal roads, to private arbitration, CBC News reported.
It would also exempt the project from the Expropriation Act as a whole, from the Railway Relocation and Crossing Act and from key parts of the Railway Safety Act and the Impact Assessment Act, according to CBC.
Parliament has already loosened the usual rules once. The High-Speed Rail Network Act was enacted through Bill C-15, which received royal assent on March 26. It changed the expropriation process for the rail network and allows notices that give a right of first refusal on land or prohibit work on it. We reported in September that Alto had bought its first parcel of land and that owners were no longer guaranteed a public hearing.
The new draft would widen the minister’s discretion to consider any factor, including the public interest, before registering a ban on work, CBC reported. Ajay Gajaria, a municipal and land-use planning lawyer, told CBC that broad use of the right of first refusal and the work prohibition would, in his view, go too far.
Gajaria also told the network he expects it to be the largest expropriation project in modern Canadian history, both by dollar value and by the number of private properties needed.
MacKinnon said the enhanced powers would let Ottawa speed up steps that could otherwise be bogged down for years. “There is no removal of due process,” he said, according to The Canadian Press. He told reporters that Montreal’s Réseau express métropolitain and Toronto’s Ontario Line also use custom land acquisition systems, CBC reported.
Ontario Conservative MP Michael Barrett said the changes would replace the Expropriation Act with a separate system for high-speed rail, adding to concerns about the project’s cost and its disruption of rural communities in eastern Ontario and Quebec, The Canadian Press reported.
Alto, the Crown corporation leading the project, told CBC that a more streamlined process does not mean less protection for affected property owners or less project oversight. It said landowners facing expropriation would receive fair compensation based on current use, market value and the financial effect on the rest of their property.
The line is designed for trains running at 300 kilometres an hour, with work on the Montreal-Ottawa leg set to start by 2030. The Canadian Press put the projected cost at $60 billion to $90 billion. The Parliamentary Budget Officer estimated in October that it could cost $75 billion to $113 billion and said going over budget was more likely than coming in under.
Opposition has also come from farm groups. A study for Quebec’s farm union argued this month that upgrading existing tracks would be a far cheaper option.
Sources: CBC News, The Canadian Press, Parliament of Canada, Justice Laws.
If you find reporting like this useful, consider supporting Canada News Media, an independently owned Canadian newsroom.
Follow Canada News Media
Get the day's top Canadian stories and our two daily 60-second news videos wherever you scroll.