Nova Scotia Liberal Leader Becky Druhan called on the Progressive Conservative government Wednesday, Nov. 25, 2026, to pause the planned AI data centre at Point Tupper, N.S., until regulations protect communities, power bills, water and the environment, The Canadian Press reported.
The project’s 95-megawatt first phase is equal to about 3.8 per cent of the highest electricity demand Nova Scotia Power has reported, according to a Canada News Media calculation. The utility said demand hit a record 2,481 megawatts during a deep freeze in January 2026. It put average hourly winter needs at about 1,700 megawatts, of which 95 megawatts would be about 5.6 per cent.
A proposed 325-megawatt expansion in 2028, subject to regulatory conditions, would bring the site to 420 megawatts, as we reported when Anthropic announced its lease. That equals about 17 per cent of the record peak, or about a quarter of the average winter figure. The comparisons set the project’s stated size against past demand. They do not forecast how much power it will draw at any hour or account for new supply.
“Ambition needs to be matched with good judgment. Announcing a big project is one thing, making sure it’s a good deal for Nova Scotians is another,” Druhan told a news conference. She said protections must be clear, enforceable and backed by law. “Handshakes aren’t protections,” she said.
The Liberals want the legislature recalled to debate safeguards. The NDP asked for an emergency debate in October.
Premier Tim Houston has repeatedly said the data centre will not raise power bills and that communities, water and the environment will be protected. In a Sept. 23 Facebook post, he listed requirements for data centres, including meeting or exceeding federal responsible-development standards, which are not binding, and providing a direct financial return to Nova Scotians. On Oct. 28, he said he did not think every business that sets up in the province needs its own law.
Houston’s office said in a statement Wednesday that it was “interesting” the provincial Liberals disagreed with the federal Liberals, and that the Carney government has supported the project. The office did not answer whether the premier would consider new regulations, The Canadian Press reported.
EverWind Fuels plans to build and own the 18,600-square-metre facility, an $8-billion project with another $2 billion planned for wind farms. Anthropic has signed a 20-year lease. The Logic reported in October that the wind farms would not be ready when the centre opens, so it would initially use existing electricity infrastructure, and that Anthropic had committed to paying for required grid upgrades and protecting existing customers from related price increases.
The call came days after U.S. President Donald Trump threatened a tax on American companies that build data centres abroad. Both Alberta and Nova Scotia said they were watching for his next move.
If you find reporting like this useful, consider supporting Canada News Media, an independently owned Canadian newsroom.
Sources: The Canadian Press; Nova Scotia Power; The Logic.
Follow Canada News Media
Get the day's top Canadian stories and our two daily 60-second news videos wherever you scroll.
X Threads Facebook Instagram LinkedIn TikTok YouTube Pinterest Reddit Substack Flipboard Newsletter RSS