The time it takes the City of Vancouver to issue a building permit for a new house has fallen by almost half since 2023 and is now the shortest since the city’s records begin in 2017, but most new-home permits still take longer than three months, according to a Canada News Media analysis of the city’s open data.
The city’s issued building permits dataset records, for every permit since 2017, how many days passed between the application receiving a permit number and the permit first being issued. For new homes in the category the city labels “New Build – Low Density Housing,” half of the 547 permits issued this year up to Nov. 19 took 154 days or less. In 2023 the median was 288.5 days, and in 2022 it was 250. The 2026 figure is the lowest for any year in the data, below the previous low of 160 days in 2025 and well below 256.5 days in 2017.
The longest waits have shrunk most. In 2023, 241 of the 696 new-house permits issued, about 35 per cent, took more than a year. So far in 2026, 38 of 547, or about 7 per cent, have. At the other end, 24.5 per cent of this year’s new-house permits were issued within 90 days, compared with 2.7 per cent in 2023 and 13.4 per cent in 2025.
Standalone laneway houses show the same pattern. Their median fell to 89 days in 2026 from 228 in 2023, and about half are now issued within 90 days. But fewer are being approved: the city has issued 133 standalone laneway permits so far this year, compared with 258 in all of 2025, 297 in 2024 and 311 in 2017.
Simple renovations, already fast, are a little faster. Lower-complexity residential renovations had a median of 23 days in 2026, down from 31 in 2023, and lower-complexity commercial and mixed-use renovations 25 days, down from 32.
The improvement does not extend to everything. Permits the city does not put in any of those four categories, which include apartment and commercial buildings, larger alterations, demolitions and other complex work, had a median of 127 days in 2026. That is faster than the 147 days of 2023 but slower than the 107.5 days of 2025, and close to the 115 days of 2017.
The volume of work being permitted is high. The 3,636 permits issued in 2026 up to Nov. 19 carry a declared project value of $5.75 billion, already more than any full year in the dataset, including $5.71 billion in 2023. A small number of large projects drive that total.
The data has limits that matter for anyone reading the trend. The elapsed-days figure starts when an application generates a permit number, not when an applicant first contacts the city, and it counts weekends and holidays. It includes time the applicant takes to answer the city’s questions or revise drawings, so it measures the whole process, not only city staff time. Permits still waiting are not in the data until they are issued, so a year that clears an old backlog can look slower and a year with many recent, quick approvals can look faster. The city also warns that dates for applications made before May 2016, when it changed permit software, may be less accurate. The records do not show why times fell, how many applications are still waiting, or how long development permits and rezonings took before a building permit was sought.
For homeowners and small builders, the figures suggest a typical new house or laneway home now clears the building-permit stage months faster than it did two or three years ago, though three in four new-house permits issued this year still took more than 90 days.
How we checked: We downloaded all 52,758 records in the City of Vancouver’s issued building permits dataset on Nov. 21, 2026 (latest issue date Nov. 19, 2026). We grouped permits by year issued and by the city’s own permit category field, and calculated the exact median, the share issued within 90 days and the share taking more than 365 days from the PermitElapsedDays field. Project values are summed from the ProjectValue field as declared on the permit. Every figure was checked twice against the downloaded file.